Republican Unitary Enterprise

Belarusian nuclear
power plant

Address:

Administrative and laboratory building (00UYA)

Vornyany village council, 2/7

Ostrovets district, Grodno region, Republic of Belarus 231220

Е-mail: belaes@belaes.by

NPP Information Center: ic@belaes.by

Phones:

Reception: +375 (1591) 4-53-59, fax: +375 (1591) 4-54-00

HR department: +375 (1591) 45-357; +375 (1591) 46-697

Accounts department: +375 (1591) 46-358

NPP Information Center: +375 1591 46 605

Purchases: +375 (1591) 4-67-19, +375 (1591) 4-67-34

Saturday, 04 April 2020

Voltage was supplied at power unit No. 2 of Belarusian NPP for own needs

Written by Department of information and public relations

On March 31, 2020, four sections of 10 kV power unit No. 2 of Belarusian NPP were energized according to the design scheme. The performance of all four sections of 10 kV power supply system was checked.

The start of voltage supply according to the standard scheme is a key event at the stage of construction of each nuclear power unit. Providing the second power unit with electricity according to the standard scheme will start full-scale commissioning of the equipment.

Last modified on Saturday, 04 April 2020
© 2010- State enterprise «Belarusian NPP». All rights reserved. At any use of materials of the web-site, the active reference is obligatory on www.belaes.by.
The web-site operates error-checking system. If you find a mistake, highlight it and press Ctrl + Enter.
Яндекс.Метрика
Development of CVR-Oktjabr'skij
Send a mistake message